Two companies seeking to build liquefied natural gas (LNG)
import terminals on Passamaquoddy Bay filed their formal
applications with the Federal Energy Regulatory Commission
(FERC) within a week of each other. Quoddy Bay LNG, which
is proposing a facility at Split Rock, Pleasant Point, filed
on December 15, and Downeast LNG, which proposes an import
terminal at Mill Cove in Robbinston, followed a week later,
on December 22. Downeast LNG also filed applications with
state officials under Maine's Natural Resources Protection
Act and Site Location of Development Law. Quoddy Bay hopes
to submit applications to state agencies in early 2007.
FERC staff now will issue a notice on its website at <www.ferc.gov>
seeking public comment and requests for intervenor status
within the next week for Quoddy Bay and sometime after that
for Downeast LNG. The comment period for each project will
extend for approximately 20 days. Intervenors will have
the right to appeal FERC's decision either through FERC
or a U.S. court of appeals.
According to Tamara Young-Allen, spokesperson for FERC's
Office of Energy Projects, there will be more opportunities
for public comment when the FERC staff begins its environmental
review. Although FERC has held some public scoping sessions
during the pre-filing process, she is not sure they will
be conducted during the formal application process. The
pre-filing process included a review of the environmental
information that is included in the formal application and
gave the public an opportunity to find out about the proposed
facilities and the environmental issues that may arise.
Also, draft resource reports were reviewed by FERC staff.
After an initial round of comments, FERC will prepare a
draft Environmental Impact Statement (EIS) that will be
open for further comments before a final EIS is issued for
each project. The cases will then be ready for a decision
by the five FERC commissioners. The commissioners, who are
appointed by the president, include three Republicans, one
independent and one Democrat. No more than three of the
commissioners can be from the same party. Young-Allen estimates
that a decision should be made within 10 to 18 months from
the date of receiving the formal applications.
There are five existing LNG terminals in the U.S., and 16
more terminals have been approved by FERC. Presently 12
LNG proposals are pending before FERC, with about 40 proposals
either pending or being discussed by the LNG industry for
North America. According to FERC's website, even if an LNG
terminal receives all federal and state approvals, "it
still must meet complicated global issues surrounding financing,
gas supply and market conditions. Many industry analysts
predict that only 12 of the 40 LNG terminals being considered
will ever be built."
Among the groups that are planning to file for intervenor
status are the three alliance members of Save Passamaquoddy
Bay, which are opposed to the LNG projects, the Maine State
Planning Office, and the Roosevelt Campobello International
Park Commission, along with other organizations and agencies.
"The realities of the developers' problems with their
proposals will become obvious now, as facts replace spin,"
says Linda Godfrey, coordinator of Save Passamaquoddy Bay-U.S.
"FERC has yet to accept these applications, and, even
if they do, they face insurmountable obstacles regarding
need, safety, alternatives and environment."
The City of Eastport and the Eastport Port Authority also
are expected to file to be intervenors in the Quoddy Bay
proceedings, according to Eastport City Manager George Finch.
"It's not that we're pro or con, but we need to protect
the interests of the city," he says.
In addition to the FERC permit, the U.S. Coast Guard must
approve a ship operating plan for LNG carriers coming to
and from the terminal, and various state permits need to
be issued. Certain Canadian officials have asked to provide
input into the FERC review process, and their comments also
will be considered by U.S. officials.
In addition, at a recent port safety forum in Eastport,
tribal officials stated that they will be working with the
Coast Guard on LNG ship safety issues, according to Pleasant
Point Passamaquoddy Governor Rick Doyle. Since aboriginal
rights to the saltwater for transportation and sustenance
were not considered in the Maine Indian Claims Settlement
Act of 1980, Doyle says the tribe will be part of the discussions
on how the bay is managed. "The tribe will be working
cooperatively with anyone so that all of our lands are safe,"
says the Passamaquoddy governor.
Along with seeking federal and state approvals, Quoddy Bay
LNG is looking to obtain a tax exemption agreement from
the Passamaquoddy Joint Tribal Council. The joint council
took no action on the Project Coordination and Tax Agreement
at its December 13 meeting, although there was considerable
discussion, according to Doyle. "It's up to the tribe
to decide if they want to continue the discussions,"
says Doyle. Last February the joint council had voted to
turn down the tax agreement, which calls for the exemption
of real and personal property taxes and the reduction of
the Tribal Employment Right Ordinance (TERO) tax for Quoddy
Bay. The tax exemption provisions would be in exchange for
lease payments to Pleasant Point amounting to an estimated
$12 million per year once the proposed LNG facility is fully
operational.
The joint council also took no action on a proposal from
Quoddy Bay to purchase 300 acres of land west of the Old
Eastport Road in Perry for $1.5 million. Quoddy Bay proposes
to use the land as a storage and staging area during the
construction process. Although it has been pointed out that
the land has a significant amount of rock that could be
turned into aggregate, or crushed stone used in construction,
which could make the land worth considerably more, Quoddy
Bay LNG Project Manager Brian Smith says the company would
not be removing aggregate from the land. He notes, "We
will have too much excavated material at the existing [LNG
terminal] site."
Quoddy Bay, though, has obtained an option to purchase a
30-acre parcel at the corner of Route 1 and Route 190 as
a site for temporary lodging for construction workers. The
actual purchase will depend on the financing of the project,
says Smith, but the company needs to start preparing for
possible construction if the project is approved. Any permits
for the lodging, including local permits, will be sought
as part of the overall LNG project.
During the three-year construction period, an average of
735 workers would be needed, according to Quoddy Bay, and
Smith says the company expects that "hundreds of workers"
will commute from local communities. Along with construction
workers, Quoddy Bay would hire dozens of non-construction
workers, such as chefs, servers, housekeepers and administrative
staff, at the modular housing facility throughout construction.
The facilities would include indoor and outdoor recreational
facilities, a large dining room, a café, laundry
facilities, private security and enough rooms for those
who decide to stay in the temporary modular housing. Smith
notes that Quoddy Bay would remove all structures from the
site after construction is completed.
Quoddy Bay LNG project
Smith says he is "very confident" that the project
will be approved by FERC because of the input received from
FERC and local stakeholders during the pre-filing process.
"We got a lot of feedback already that's been very
positive."
"Unlike many other prior applicants for such licenses,
Quoddy Bay has had the advantage of having a thorough review
process by FERC before filing its formal application,"
says Smith. "This new FERC process has been a success
from our perspective and we've been able to incorporate
all the comments received from FERC, other federal and state
agencies and stakeholders throughout the region into our
formal filing."
Quoddy Bay LNG's 2.0 billion cubic feet per day LNG import,
storage and regasification facility proposal includes a
pier extending from Split Rock, two vessel berths, and a
regasification process platform; the Split Rock support
facility on the reservation, which includes a control building,
office and warehouse; the LNG transfer pipelines and vapor
return line, which would connect the pier to the onshore
storage and regasification facility that includes three
storage tanks, electric generation equipment and a regasification
facility on land in Perry. The proposal also includes a
35.8-mile pipeline from the LNG terminal to the Maritimes
& Northeast natural gas pipeline in the town of Princeton.
The Maritimes and Northeast Pipeline expansion for the Quoddy
Bay Project is detailed in a report prepared by Maritimes
& Northeast Pipeline and submitted to FERC in September.
Quoddy Bay LNG is aiming to begin operations by the winter
of 2009-2010.
Downeast LNG project
Downeast LNG's application to FERC is for an LNG import
terminal in Robbinston and a 31-mile pipeline that will
connect to the Maritimes & Northeast Pipeline at Baileyville.
"This is a major milestone for our project, and we
are grateful to local residents and members of our team
who have helped us keep this project moving forward,"
said Dean Girdis, president of Downeast LNG, in a prepared
release. "This is a safe, environmentally sound project
and we are confident that it will be approved after a rigorous
review by FERC and other federal and state agencies."
The proposed facility would consist of two storage tanks,
a regasification plant and a pier to receive LNG carriers.
The facility would have a storage capacity of 320,000 cubic
meters, with an output capacity of 500 million standard
cubic feet per day (mmscfd) and peaking capacity of 625
mmscfd. The proposal also includes a 31-mile pipeline that
would connect the facility to the Maritimes and Northeast
Pipeline that runs from Nova Scotia through Maine to southern
New England.
Downeast LNG hopes to have all of its approvals in hand
by the end of 2007 and to begin construction by late 2007
or early 2008. Girdis hopes that the terminal facility and
pipeline connection would be ready to receive LNG shipments
by late 2010 or early 2011. |